Residents of Roodepoort and Johannesburg south will have some respite from ongoing water issues as Rand Water has completed maintenance work at the Eikenhof pump station.
After going more than a week with no water supply due to the 1-month long maintenance project, affected areas will have water flowing as Eikenhof has been pumping at 100% since Wednesday, 10 July.
The maintenance project at Eikenhof was scheduled to run from 24 to 12 July, but was completed ahead of the 18-day deadline on 08 July.
All Johanneburg water systems that are supplied by Eikenhof are improving and supplying fairly to normally.
#RandWaterMaintenance #Eikenhof #JoburgUpdates. ^N pic.twitter.com/Wd29X6ayD9
— Johannesburg Water (@JHBWater) July 10, 2024
The scheduled maintenance from 22 June to 29 July is still underway at the Palmiet and Daleside Booster station as follows:
Palmiet will be pumping at 60% for 8-hours
- 15 July – Palmiet System
Palmiet pumping will be reduced to 68% for 50-hours
- 29 July – Palmiet System
Palmiet pumping will be reduced to 76% for 40-hours
Also read: Police hunt for duo linked to murder of SA athlete Jacques Frietag